Crane supports
Tower cranes are usually supplied on a hire basis, with the client being responsible for the design and construction of the base upon which the crane will be erected. Details of loading are provided by the crane supplier and the base is most commonly designed as a temporary structure, although sometimes a crane base will be incorporated into the permanent structure to save on cost and time.
Loads are given in two forms, ‘in service’ loads, where the crane is functioning and wind speeds are restricted (ie cranes will not operate at high wind speeds), and ‘out of service’ loads, where the crane is not being used but maximum wind speeds may occur.
The location for a crane should be carefully selected to provide a maximum working radius, and when two cranes are being used on the same site mast heights and jib lengths must be considered so that they do not clash.
Cranes are typically structured around two rails at their base between 4.5m-10m apart with wheels in each corner. Cranes are not normally tied down, so sufficient kentledge must be provided to ensure vertical loading from the crane passes through the rails and into the foundation. The foundation is designed so that the unfactored loading from the crane and the unfactored loading from the foundation itself create a bearing pressure which is less than the allowable bearing pressure of the soil.
Various foundation types can be selected depending on the ground conditions:
- Where possible a structural fill can be compacted and used to support a crane with the load spreading through layers of track support at 45° in to the soil strata below.
- When loads from the crane increase, reinforced concrete foundations may be required. This can involve a series of reinforced concrete beams used to support line loads as a result of the crane loading.
- When ground conditions are particularly poor, piled foundations may be necessary. Careful design is required to ensure that reinforcement at the top of the pile top does not cause problems for positioning the mast base section of the crane.
[edit] Related articles on Designing Buildings Wiki
- Avoiding crane collapses.
- Bituminous mixing and laying plant.
- CDM.
- Compressed air plant.
- Concreting plant.
- Construction plant.
- Crane regulations.
- Deleterious materials.
- Designers.
- Design liability.
- Demolition.
- Earth-moving plant.
- Electromagnetic overhead cranes.
- Excavating plant.
- Facade retention.
- Falsework.
- Forklift truck.
- Formwork.
- Gantry.
- Health and Safety.
- Scaffolding.
- Temporary works
- Trench support.
- Types of crane.
[edit] External references
- BS5975:2008 + A1: 2001 Code of Practice for Temporary Works Procedures and the Permissible Stress Design of Falsework (BSI 2011).
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February